    How many days

    Hello All,

    How do I calculate how many working days between two
    dates. Using the UK holiday calender, I have a list of
    additional holiday dates that are non working for the
    company. I have named this list as "leaves". I can not
    get the formula right. Help would be appreciated. Thanks.

    S

  2. #2
    Chip Pearson
    Guest

    Re: How many days

    Use the NETWORKDAYS function.

    =NETWORKDAYS(start_date,end_date, Leaves)


    --
    Cordially,
    Chip Pearson
    Microsoft MVP - Excel
    Pearson Software Consulting, LLC
    www.cpearson.com


    <[email protected]> wrote in message
    news:[email protected]...
    > Hello All,
    >
    > How do I calculate how many working days between two
    > dates. Using the UK holiday calender, I have a list of
    > additional holiday dates that are non working for the
    > company. I have named this list as "leaves". I can not
    > get the formula right. Help would be appreciated. Thanks.
    >
    > S




  3. #3
    Guest

    Re: How many days

    Hi

    Have a look at NETWORKDAYS(). I think you need to have the Analysis Toolpak
    add-in loaded for this function.

    --
    Andy.


    <[email protected]> wrote in message
    news:[email protected]...
    > Hello All,
    >
    > How do I calculate how many working days between two
    > dates. Using the UK holiday calender, I have a list of
    > additional holiday dates that are non working for the
    > company. I have named this list as "leaves". I can not
    > get the formula right. Help would be appreciated. Thanks.
    >
    > S




  4. #4
    Guest

    Re: How many days

    Thanks. This is great.

    S

    >-----Original Message-----
    >Use the NETWORKDAYS function.
    >
    >=NETWORKDAYS(start_date,end_date, Leaves)
    >
    >
    >--
    >Cordially,
    >Chip Pearson
    >Microsoft MVP - Excel
    >Pearson Software Consulting, LLC
    >www.cpearson.com
    >
    >
    ><[email protected]> wrote in message
    >news:[email protected]...
    >> Hello All,
    >>
    >> How do I calculate how many working days between two
    >> dates. Using the UK holiday calender, I have a list of
    >> additional holiday dates that are non working for the
    >> company. I have named this list as "leaves". I can not
    >> get the formula right. Help would be appreciated.

    Thanks.
    >>
    >> S

    >
    >
    >.
    >


+ Reply to Thread

Thread Information

Users Browsing this Thread

There are currently 1 users browsing this thread. (0 members and 1 guests)

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts

Search Engine Friendly URLs by vBSEO 3.6.0 RC 1