Display latest arrival date

  1. #1
    Annabelle
    Guest

    Display latest arrival date

    CELLS
    P5 is the original date and Q5 through T5 are cells for up to four
    possible move dates (schedule changes). U5 is the target arrival date.

    QUESTION
    In U5, I want to show the most current target arrival date. If there
    are no schedule changes, this would be P5, but if there is a schedule
    slip, I want the most current date to appear. If the schedule slipped
    once, this would be Q5; if the schedule has slipped three times, this
    would be S5.

    Is there a formula that could accomplish this task?

    EXAMPLE1
    P5 - 02/01/06
    Q5 -
    R5 -
    S5 -
    T5 -
    U5 - 02/01/06

    EXAMPLE2
    P5 - 02/01/06
    Q5 - 02/05/06
    R5 - 02/10/06
    S5 -
    T5 -
    U5 - 02/10/06

    EXAMPLE3
    P5 - 02/01/06
    Q5 - 02/05/06
    R5 - 02/10/06
    S5 - 02/11/06
    T5 - 02/15/06
    U5 - 02/15/06


  2. #2
    Jim May
    Guest

    Re: Display latest arrival date

    In Cell U5 enter =max(P5:T5)

    "Annabelle" <[email protected]> wrote in message
    news:[email protected]...
    > CELLS
    > P5 is the original date and Q5 through T5 are cells for up to four
    > possible move dates (schedule changes). U5 is the target arrival date.
    >
    > QUESTION
    > In U5, I want to show the most current target arrival date. If there
    > are no schedule changes, this would be P5, but if there is a schedule
    > slip, I want the most current date to appear. If the schedule slipped
    > once, this would be Q5; if the schedule has slipped three times, this
    > would be S5.
    >
    > Is there a formula that could accomplish this task?
    >
    > EXAMPLE1
    > P5 - 02/01/06
    > Q5 -
    > R5 -
    > S5 -
    > T5 -
    > U5 - 02/01/06
    >
    > EXAMPLE2
    > P5 - 02/01/06
    > Q5 - 02/05/06
    > R5 - 02/10/06
    > S5 -
    > T5 -
    > U5 - 02/10/06
    >
    > EXAMPLE3
    > P5 - 02/01/06
    > Q5 - 02/05/06
    > R5 - 02/10/06
    > S5 - 02/11/06
    > T5 - 02/15/06
    > U5 - 02/15/06
    >




  3. #3
    Annabelle
    Guest

    Re: Display latest arrival date

    Excellent! Thank you for your help.


  4. #4
    Minitman
    Guest

    Re: Display latest arrival date

    In U5 put this formula:
    =IF(T5="",IF(S5="",IF(R5="",IF(Q5="",P5,Q5),R5),S5),T5)
    (Don't forget to format P5 - U5 as "Date")

    This is assuming you don't need to go any further as there is a limit
    of 7 nested IFs in Excel.

    This is al sp assuming that the contents of P5 thru T5 have either a
    date or are empty. If they have a "0" in them then change the "" to
    0.

    HTH

    -Minitman

    On 21 Feb 2006 05:12:40 -0800, "Annabelle" <[email protected]>
    wrote:

    >CELLS
    >P5 is the original date and Q5 through T5 are cells for up to four
    >possible move dates (schedule changes). U5 is the target arrival date.
    >
    >QUESTION
    >In U5, I want to show the most current target arrival date. If there
    >are no schedule changes, this would be P5, but if there is a schedule
    >slip, I want the most current date to appear. If the schedule slipped
    >once, this would be Q5; if the schedule has slipped three times, this
    >would be S5.
    >
    >Is there a formula that could accomplish this task?
    >
    >EXAMPLE1
    >P5 - 02/01/06
    >Q5 -
    >R5 -
    >S5 -
    >T5 -
    >U5 - 02/01/06
    >
    >EXAMPLE2
    >P5 - 02/01/06
    >Q5 - 02/05/06
    >R5 - 02/10/06
    >S5 -
    >T5 -
    >U5 - 02/10/06
    >
    >EXAMPLE3
    >P5 - 02/01/06
    >Q5 - 02/05/06
    >R5 - 02/10/06
    >S5 - 02/11/06
    >T5 - 02/15/06
    >U5 - 02/15/06



+ Reply to Thread

Thread Information

Users Browsing this Thread

There are currently 1 users browsing this thread. (0 members and 1 guests)

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts

Search Engine Friendly URLs by vBSEO 3.6.0 RC 1