Compute Project Start/End Date

  1. #1
    Registered User
    Join Date
    01-28-2011
    Location
    Morris Plains, NJ
    MS-Off Ver
    Excel 2003
    Posts
    1

    Compute Project Start/End Date

    I need help computing the Project Start Dates for each US state marketing campaign, under the Attached File "Strategic Plan" tab.

    Column E: Total Number of State Contacts
    Column F: Estimated Processing Time - calculated as =E2/(9*4.33) meaning, I could process 9 contacts per week in a given month, resulting in an answer in months.
    Column G: Project Begin Date: If I started my first state (Row 2), on February 1, 2011 (provided it's a weekday, because it will only be workdays), when would I complete the project (February 1, 2011 + results of Column F)
    Column H: Project End Date: What date will the project be completed if began on February 1, 2011 for Row 2 and so on?

    Column G and H are dependent upon each others similar to that in a Gannt's predecessor task, where Column G (Project Start Date) is at 02/01/2011, the processing time is "x.xx weeks", giving a task completion date of xx/xx/2011, which date also serves as Column G (Project Start Date) of Row 3, and the process continues until all the row data has been completed.

    Thanks,
    Penny
    Attached Files Attached Files

+ Reply to Thread

Thread Information

Users Browsing this Thread

There are currently 1 users browsing this thread. (0 members and 1 guests)

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts

Search Engine Friendly URLs by vBSEO 3.6.0 RC 1