Hi all,
Need some help please. I can import excel generated project to a new MS Project and it works as fine. Standard functionality. What I am trying to do is updating % Complete on MS Project with the % Complete on Excel after the import was done. I don’t want to use copy and past as becomes messy if you have thousands of line items. I want to push the updates from excel, I assume via a VB to MS Projects so it does the updates automatically. The Unique number in MS Projects and Excel that are the same.

I hope this make sense.
Any ideas?

Thank you,
Pierre