It should have been =NETWORKDAYS(C14+2,D14+2)
--
HTH
Bob Phillips
(remove xxx from email address if mailing direct)
<[email protected]> wrote in message
news:[email protected]...
> hello Tom,
>
> Thanks a lot. If I quote your formula I receive 3 working days but if I
> quote your modified formila such as : =NETWORKDAYS(C14-5,D14-5) I
> received a good result.
> try with start date March 18 and end date March 29
> Regards,
> Patrick
>