Hi all.
I am making an inventory list and want to have a reorder date based on: current inventory, usage pr. day, safety stock and reorder time (days).
How do I go about to have the reorder date calculated?
Best regards.
Stefan Pall.
Hi all.
I am making an inventory list and want to have a reorder date based on: current inventory, usage pr. day, safety stock and reorder time (days).
How do I go about to have the reorder date calculated?
Best regards.
Stefan Pall.
=today()+roundup((CurrentInventory-safetyStock) divided by usage pr day)-reorder time
Best of luck.
Chris
Click * below if this answer helped
Thanks Chris.
Worked fine.
Just the thing I was looking for.
Best regards.
Stefan Pall.
Hi Stefan
If you are happy with this, please click the add reputation and mark the thread as closed.
Regards Chris