+ Reply to Thread
Results 1 to 12 of 12

Forecast completion date from original plan and actual work done

  1. #1
    Forum Contributor
    Join Date
    07-12-2015
    Location
    Dubai,UAE
    MS-Off Ver
    Office 365
    Posts
    425

    Forecast completion date from original plan and actual work done

    I have a table of values showing a time period ( with start and finish dates) and corresponding cumulative % values. ( THIS IS THE PLAN)

    Now I have an actual % value at a particular date.
    I need to forecast completion date based on the actual % and plan.
    I have manually calculated the result as shown in attachment.


    Thanks in advance.
    Attached Files Attached Files

  2. #2
    Forum Expert José Augusto's Avatar
    Join Date
    10-29-2014
    Location
    Portugal
    MS-Off Ver
    2013-2016
    Posts
    3,329

    Re: Forecast completion date from original plan and actual work done

    Hi

    I do not know which calculus you have done. The result in my approach is not the same as yours.
    Try this
    In column M from M2 use this formula and drag down
    Formula: copy to clipboard
    Please Login or Register  to view this content.

    In I4 use this formula to get the forecast completion date
    Formula: copy to clipboard
    Please Login or Register  to view this content.

    Note: M6=0

  3. #3
    Forum Contributor
    Join Date
    07-12-2015
    Location
    Dubai,UAE
    MS-Off Ver
    Office 365
    Posts
    425

    Re: Forecast completion date from original plan and actual work done

    Hi Jose Augusto,

    Thanks for the reply.
    My approach was different
    I was calculating the % value closest to the actual available on the plan..
    Then adjusting the duration for the difference..
    And from that point, continuing the distribution as per original plan..
    Your approach also gives almost the same results...I have to test it further and then will let you know..
    Could you please explain what is calculated in column M?

  4. #4
    Forum Expert José Augusto's Avatar
    Join Date
    10-29-2014
    Location
    Portugal
    MS-Off Ver
    2013-2016
    Posts
    3,329

    Re: Forecast completion date from original plan and actual work done

    Hi

    Sorry for the late answer.

    The M2 value is the result of the difference between the actual value verified (20%) and the estimated value planned in K2, that is, on March 1 the estimated value in the plan was FORECAST.ETS(K2,$D$2:$D$5,$C$2:$C$5), approximately 60.47% of which only 20% is performed: 20% -60% = -40%. The formula does the same for the other dates , based on the initial plan.

  5. #5
    Forum Guru Bo_Ry's Avatar
    Join Date
    09-10-2018
    Location
    Thailand
    MS-Off Ver
    MS 365
    Posts
    7,211

    Re: Forecast completion date from original plan and actual work done

    Please try at I5

    =C5-B2-(I2-LOOKUP(I2,N(+D1:D5)))/(LOOKUP(I2,N(+D1:D5),D2:D5)-LOOKUP(I2,N(+D1:D5)))*LOOKUP(I2,N(+D1:D5),E2:E5)+I3
    Attached Files Attached Files

  6. #6
    Forum Contributor
    Join Date
    07-12-2015
    Location
    Dubai,UAE
    MS-Off Ver
    Office 365
    Posts
    425

    Re: Forecast completion date from original plan and actual work done

    Hi Bo_Ry,

    Thanks for your reply.
    I think there should be a modification in the formula because it will not work unless the lookup % is first value in the table.
    Can you modify the formula accordingly?

  7. #7
    Forum Guru Bo_Ry's Avatar
    Join Date
    09-10-2018
    Location
    Thailand
    MS-Off Ver
    MS 365
    Posts
    7,211

    Re: Forecast completion date from original plan and actual work done

    Please provide more samples with expected results.

  8. #8
    Forum Contributor
    Join Date
    07-12-2015
    Location
    Dubai,UAE
    MS-Off Ver
    Office 365
    Posts
    425

    Re: Forecast completion date from original plan and actual work done

    Hi Bo_Ry,

    Please find attached.

    As of 22-Mar-18, if actual is 85% it means that work is progressing exactly as per plan
    So the completion date should be same as in plan
    Attached Files Attached Files

  9. #9
    Forum Contributor
    Join Date
    07-12-2015
    Location
    Dubai,UAE
    MS-Off Ver
    Office 365
    Posts
    425

    Re: Forecast completion date from original plan and actual work done

    Hi Bo_Ry,

    I managed to get a working formula but its very long and not elegant.
    Hope you can help..

    Formula: copy to clipboard
    Please Login or Register  to view this content.

  10. #10
    Forum Expert José Augusto's Avatar
    Join Date
    10-29-2014
    Location
    Portugal
    MS-Off Ver
    2013-2016
    Posts
    3,329

    Re: Forecast completion date from original plan and actual work done

    Hi

    For my formula to work, I need to have the start date associated with the 0% value run in the same column as the other end-of-period dates. I made that adaptation.
    The formula that I propose, determines the date of completion of the project according to a date and a percentage of the executed, taking into account what was planned.
    See if this serves you.
    Formula: copy to clipboard
    Please Login or Register  to view this content.
    Attached Files Attached Files

  11. #11
    Forum Contributor
    Join Date
    07-12-2015
    Location
    Dubai,UAE
    MS-Off Ver
    Office 365
    Posts
    425

    Re: Forecast completion date from original plan and actual work done

    Hi Jose Augusto,

    Thank u so much..this works perfectly..
    Brilliant concept used in the formula..

  12. #12
    Forum Expert José Augusto's Avatar
    Join Date
    10-29-2014
    Location
    Portugal
    MS-Off Ver
    2013-2016
    Posts
    3,329

    Re: Forecast completion date from original plan and actual work done

    You are welcome.

    Do not forget to mark this thread as SOLVED.

    Thanks.

+ Reply to Thread

Thread Information

Users Browsing this Thread

There are currently 1 users browsing this thread. (0 members and 1 guests)

Similar Threads

  1. [SOLVED] Schedule Vs. Actual completion dates
    By nagesh.tvsr in forum Excel Formulas & Functions
    Replies: 10
    Last Post: 10-24-2022, 04:27 PM
  2. [SOLVED] Actual Receipt Date Vs. Original Receipt Date (Compare & Provide Result)
    By Rajeshkumar R in forum Excel Programming / VBA / Macros
    Replies: 3
    Last Post: 05-05-2018, 07:06 AM
  3. Forecast Value by checking plan and Actual Manhours
    By velu130468 in forum Excel Programming / VBA / Macros
    Replies: 0
    Last Post: 12-29-2017, 06:50 AM
  4. Calculate completion date from start date and duration - only work days
    By Robsheep in forum Excel Formulas & Functions
    Replies: 6
    Last Post: 03-23-2015, 03:31 AM
  5. Pivot Table - Forecast at completion based on actuals to date
    By ramgouda in forum Excel Formulas & Functions
    Replies: 0
    Last Post: 06-27-2014, 04:37 PM
  6. estimation vs actual completion graph
    By sanlen in forum Excel General
    Replies: 2
    Last Post: 10-06-2010, 07:26 AM
  7. Forecast the Completion Date and Time
    By Grock258 in forum Excel General
    Replies: 2
    Last Post: 07-24-2008, 12:05 PM

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts

Search Engine Friendly URLs by vBSEO 3.6.0 RC 1