    Good morning,

    I am trying to find a way to have the milestone that is in a task, reflected in the total project timeline. For example, in the attached, I have the milestone conditional formatted to shade in black; I'd like that to reflect in the appropriate week in the total project timeline. I've not been able to figure out what I need to add in order to do that. Thank you so much!
    Attached Files Attached Files

  2. #2
    Valued Forum Contributor
    Join Date
    04-24-2020
    Location
    Woodbridge, VA
    MS-Off Ver
    2016
    Posts
    434

    Re: Conditional format project timeline based on milestone in sub task

    Hi - to make sure I understand, are you saying that if Column A has a M you want a cell to be colored black?

  3. #3
    Registered User
    Join Date
    05-03-2021
    Location
    Virginia, US
    MS-Off Ver
    2010
    Posts
    4

    Re: Conditional format project timeline based on milestone in sub task

    Hello! yes that is correct! I can get it to do that in the task but can't figure out how to get it in the overall project timeline that is above it. (For example I can get it show black in row 10 but not row 7.)

  4. #4
    Valued Forum Contributor
    Join Date
    04-24-2020
    Location
    Woodbridge, VA
    MS-Off Ver
    2016
    Posts
    434

    Re: Conditional format project timeline based on milestone in sub task

    OK so if I put a M in 7A then H7 to AE7 turn black.

  5. #5
    Forum Expert
    Join Date
    05-05-2015
    Location
    UK
    MS-Off Ver
    Microsoft Excel for Microsoft 365 MSO (Version 2402 Build 16.0.17328.20068) 64-bit
    Posts
    28,597

    Re: Conditional format project timeline based on milestone in sub task

    Try this as the CF formula for row 7

    =SUMPRODUCT(($D$8:$D$200>=H$3)*($E$8:$E$200<=I$3)*($A$8:$A$200="M"))
    Attached Files Attached Files

  6. #6
    Registered User
    Join Date
    05-03-2021
    Location
    Virginia, US
    MS-Off Ver
    2010
    Posts
    4

    Re: Conditional format project timeline based on milestone in sub task

    This is great but have a question. I modified this so that it would only calculate through the current task (versus all). For example, for row 7, I just wanted it to highlight where there is an M in rows 8-24. Doing that eliminated it from highlighting for Ms that are in rows for other programs so that's awesome. However, when I put an M in rows 10 and 11 (weeks 3 and 4), columns I and J (weeks 2 and 3) highlight. So it appears to highlight the cell prior to what matches in column A. Is there a way to fix that? Am I explaining that right?
    Last edited by AliGW; 05-04-2021 at 12:10 PM. Reason: PLEASE don't quote unnecessarily!

  7. #7
    Forum Expert
    Join Date
    05-05-2015
    Location
    UK
    MS-Off Ver
    Microsoft Excel for Microsoft 365 MSO (Version 2402 Build 16.0.17328.20068) 64-bit
    Posts
    28,597

    Re: Conditional format project timeline based on milestone in sub task

    Not in the file I sent: columns J and K are highlighted (where there is a 1 in column 6)

    =SUMPRODUCT(($D$8:$D$24>=H$3)*($E$8:$E$24<=I$3)*($A$8:$A$24="M")) in row 6

    will show 1 for weeks 3 and 4

  8. #8
    Forum Expert
    Join Date
    05-05-2015
    Location
    UK
    MS-Off Ver
    Microsoft Excel for Microsoft 365 MSO (Version 2402 Build 16.0.17328.20068) 64-bit
    Posts
    28,597

    Re: Conditional format project timeline based on milestone in sub task

    Check I did not make an error: H$3 not $H3

  9. #9
    Registered User
    Join Date
    05-03-2021
    Location
    Virginia, US
    MS-Off Ver
    2010
    Posts
    4

    Re: Conditional format project timeline based on milestone in sub task

    You're absolutely correct; the file you sent was correct. I must have had a conflict when I tried to recreate your solution. Thank you so much for your help!!!!

  10. #10
    Forum Expert
    Join Date
    05-05-2015
    Location
    UK
    MS-Off Ver
    Microsoft Excel for Microsoft 365 MSO (Version 2402 Build 16.0.17328.20068) 64-bit
    Posts
    28,597

    Re: Conditional format project timeline based on milestone in sub task

    Glad it's sorted.

    If that takes care of your original question, please select Thread Tools from the menu link above and mark this thread as SOLVED.

    Also, you may not be aware that you can thank those who have helped you by clicking the small star icon located in the lower left corner of the post in which the help was given. By doing so you can add to the reputation(s) of those who helped.

+ Reply to Thread

Thread Information

Users Browsing this Thread

There are currently 1 users browsing this thread. (0 members and 1 guests)

Similar Threads

  1. [SOLVED] Progression %age per Milestone per Project....
    By sunriver61 in forum Excel Charting & Pivots
    Replies: 7
    Last Post: 07-25-2020, 07:52 PM
  2. [SOLVED] Autopopulate schedule- by task / from milestone dates
    By mattyb_uk in forum Excel General
    Replies: 0
    Last Post: 01-27-2020, 07:24 AM
  3. Interactive Timeline/Milestone adding Shapes--No icons
    By Mauricegetsit in forum Excel General
    Replies: 0
    Last Post: 01-17-2017, 05:17 PM
  4. Multiple questions about Excel project timeline, % formulas, refresh timeline
    By Please Help in forum Excel Formulas & Functions
    Replies: 2
    Last Post: 07-27-2016, 07:13 PM
  5. Timeline-SDLC-Milestone-Tollgate Template
    By mycon73 in forum Excel General
    Replies: 3
    Last Post: 09-30-2014, 04:39 AM
  6. Conditional Formatting Formula's for Project Timeline
    By bunchomunkies in forum Excel Formulas & Functions
    Replies: 3
    Last Post: 04-30-2013, 11:41 AM
  7. [SOLVED] Project Timeline with Dynamic Date Range Based on User Input
    By Rollinstone12 in forum Excel General
    Replies: 2
    Last Post: 10-28-2012, 10:07 AM

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts

Search Engine Friendly URLs by vBSEO 3.6.0 RC 1