Hello, I have what seems a simple question, but it drives me crazy and I can not figure it out.
Here is the situation.
I have a project that Will take 252 work days to complete if 1 crew is working. I need to complete the project much sooner, so I want to have 4 crews working. 3 crews working the full time of of the project, and 1 crew working the partial time. I want the project to be over in 83 work days or sooner.
How can I setup, to manipulate the amount of days each crew will work, where the output will give me the total work days it would take to complete the project, with the current crew schedule, and show the completion date?
Seems pretty simple, but I just cant figure it out. Thank you for support.
Bookmarks