Conditional formating on Gantt for delayed tasks

  1. #1
    Registered User
    Join Date
    09-05-2019
    Location
    Canada
    MS-Off Ver
    Microsoft Office Professional Plus 2019
    Posts
    2

    Conditional formating on Gantt for delayed tasks

    Hello Forum,
    I truly hope someone can help with this:
    I found a template for a Gantt chart that works really well, except that I need cells turn red if the tasks are delayed.
    Is there any way to do that? What I’m basically looking for is a way to show at a glance the delayed tasks, due to completion percentage or due date.
    I have attached the template: Task A to E have the original conditional formatting and Task 1 to 5 is what I need.

    Thank you so much in advance for your help.
    Attached Files Attached Files

  2. #2
    Forum Expert tim201110's Avatar
    Join Date
    10-23-2011
    Location
    Russia
    MS-Off Ver
    2016, 2019
    Posts
    2,357

    Re: Conditional formating on Gantt for delayed tasks

    blue=AND(1/IFERROR(1/FLOOR.MATH($D9*($F9-$E9+1),1),1)+$E9-1<=I$5,$E9<=I$5,$F9>=I$5)
    green=AND($E9<=I$5,1/IFERROR(1/FLOOR.MATH($D9*($F9-$E9+1),1),1)+$E9-1>=I$5,$F$1>=1/IFERROR(1/FLOOR.MATH($D9*($F9-$E9+1),1),1)+$E9-1)
    red=AND(1/IFERROR(1/FLOOR.MATH($D9*($F9-$E9+1),1),1)+$E9-1<=I$5,1/IFERROR(1/FLOOR.MATH($D9*($F9-$E9+1),1),1)+$E9-1<$F9,$F$1<$F9,$F9>=I$5)
    in f1 Today()

  3. #3
    Registered User
    Join Date
    09-05-2019
    Location
    Canada
    MS-Off Ver
    Microsoft Office Professional Plus 2019
    Posts
    2

    Re: Conditional formating on Gantt for delayed tasks

    Thank you so much tim201110!!
    I'm getting really closer!!!, although I'm think I'm doing something wrong.
    I have applied the formulas and I have added one more conditional format to show the current day, but task D should be blue, task E should be half green, half blue and task F should be green. Do you think there is a way to express that? I have attached the file with your formulas from Task A to F and the sample as it should be from Task 1 to 6.
    Attached Files Attached Files

  4. #4
    Forum Expert tim201110's Avatar
    Join Date
    10-23-2011
    Location
    Russia
    MS-Off Ver
    2016, 2019
    Posts
    2,357

    Re: Conditional formating on Gantt for delayed tasks

    different approach
    added 2 columns
    Attached Files Attached Files

+ Reply to Thread

Thread Information

Users Browsing this Thread

There are currently 1 users browsing this thread. (0 members and 1 guests)

Similar Threads

  1. Gantt chart add multiple start / stop tasks
    By Martines91 in forum Excel Charting & Pivots
    Replies: 18
    Last Post: 06-09-2022, 04:19 PM
  2. Gantt chart with Tasks Userform
    By doriangrey in forum Excel Charting & Pivots
    Replies: 1
    Last Post: 03-23-2016, 09:25 AM
  3. Gantt chart with daily repeated tasks spanning midnight
    By Driz79 in forum Excel Charting & Pivots
    Replies: 1
    Last Post: 02-25-2016, 03:21 PM
  4. Gantt chart with daily repeated tasks spanning midnight
    By Driz79 in forum Excel Charting & Pivots
    Replies: 0
    Last Post: 02-25-2016, 10:00 AM
  5. Gantt chart - multiple tasks in a single row?
    By ABSTRAKTUS in forum Excel Programming / VBA / Macros
    Replies: 0
    Last Post: 05-23-2012, 01:02 PM
  6. Gantt chart with conditional formating
    By blacknails28 in forum Excel Charting & Pivots
    Replies: 0
    Last Post: 07-20-2010, 12:48 AM
  7. Replies: 1
    Last Post: 08-29-2006, 07:21 AM

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts

Search Engine Friendly URLs by vBSEO 3.6.0 RC 1