Hello All,
I am new in the forum, I hope that I can get help. here is my problem:
my task WK09 is 18 hour long. I know that I need to finish this task on Wednesday 5/27/2020 (end of the shift). I am not available every day to work on this task, here is the schedule: Monday no work, Tuesday from 10:00am to 2:00pm, Wednesday from 8:00am to 4:00pm, Thursday from 10:00am to 3:00pm, Friday from 11:00am to 3:00pm, Saturday from 10:00am to 1:00pm, and Sunday no work.
What is the formula that will allow me to find the starting date?
thank you for your help