As the title states, i have a column of dates provided by another program. I would like to run a code that will go through that column and automatically change any dates that fall on weekends to the next working day. Thank you in advance.
As the title states, i have a column of dates provided by another program. I would like to run a code that will go through that column and automatically change any dates that fall on weekends to the next working day. Thank you in advance.
You can use WORKDAY, so something like
modify sheet and column reference as appropriatePlease Login or Register to view this content.
Last edited by XLent; 01-25-2021 at 04:58 AM. Reason: modified Sheet Name to better illustrate purpose of .Parent in Evaluate call, 2nd update for typo!