    Question Start workday,Gantt chart

    Hello,

    I am trying to create a fully flexible planning time-table for monthly tasks being performed ('planning' sheet, row 40:82).
    All tasks are due on a specific working day (column H) and based on the month/year selection the effective deadline dates are calculated in E4:F38 in that sheet.

    Everything is working nicely so far, however I'm having a bit trouble on the fine-tuning part:
    In order for the project timeline chart (Gantt-chart) to properly visualize on the 'Gantt' sheet I need start dates and duration. Duration is a manual input and the start date (column C) is currently calculated =[@Deadline]-[@Duration]. However this simple calculation would include weekend/holidays, which results in an incorrect chart result.

    Just to illustrate using row 43:
    The task 'BPC open for input' is due on Monday 03-Feb-2014, 00:00. The duration is 2 work days. The current calculation for the start date in C43 is Saturday, 01-Feb-2014 00:00. However the correct start date should be 30-Jan-2014 00:00 as weekend shouldn't be counted as workdays. So I'd like to visualize on the chart that the task lasts 2 workdays, however lasts for 4 (2 days work, 2 days weekend) days in total.
    Additionally I wonder if for 'cosmetic' purposes somehow weekend or holidays could be included in the plot area (currently I just used manual text boxes for illustration).

    I hope I could comprehensibly explain the issue and feel free to use what I built so far for your own purpose. I think it's one of my more fancy developments as it'll save quite a bit of time of planning monthly recurring tasks.

    Brgrds,
    Daniel
    Attached Files Attached Files

Thread Information

Users Browsing this Thread

There are currently 1 users browsing this thread. (0 members and 1 guests)

Similar Threads

  1. Gantt chart showing Start and Finish Date
    By scottiebell in forum Excel Charting & Pivots
    Replies: 7
    Last Post: 02-21-2014, 04:46 PM
  2. Replies: 5
    Last Post: 10-04-2012, 07:01 AM
  3. Replies: 0
    Last Post: 07-13-2012, 06:40 PM
  4. Replies: 8
    Last Post: 12-09-2008, 12:38 PM
  5. [SOLVED] In a GANTT, how do I get diff projects to start later on chart
    By Tim in forum Excel Charting & Pivots
    Replies: 1
    Last Post: 10-01-2005, 10:05 AM

Tags for this Thread

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts

Search Engine Friendly URLs by vBSEO 3.6.0 RC 1