My trouble is that I have a start date and an end date for a certain task and a number of business days it will take to get from one to the other.
For example:
Start Date - July 13
Number of Business days to complete task - 4
End Date - July 19
Obviously July 19 is NOT 4 days away from July 13 but it's calculated that way in my data because of the weekend.
I want my gantt chart to show the weekend days....but instead of the regular "red" bar denoting working days - I wan't those days to be greyed out as non-working days.
Right now, my gantt would show the task starting on July 13, the red bar progressing through July 17, and then a gap between July 17 and July 19 (when the next task is scheduled to start)
I've attached the file I'm working with. Relevant worksheets are:
PRELIM. SCHEDULE (this tries to address the issue with a stack bar chart - I PREFER THIS OPTION)
PRELIM. GANTT (this is an attempt at using conditional formatting)
Thanks in advance for any help!
Bookmarks