Hello all,
This one might be a tough one. Here is my scenario. We do 'X' amount of "Jobs" a Month. They vary from month to month. My boss wants to know the percentage of jobs done to date each month. The twist is he wants them based out of 100% daily. Meaning if we are on the 10th day and there are 20 work days, and 50 "Jobs", if we've competed 25 "Jobs" it should reflect 100% compliance.12 jobs completed would show %50 etc. It's hard for me to explain. But I will try my best to answer any and all questions.
Our issue is that we are going through the "jobs" too quickly and during the later days of the month are being with less to do. We are hoping this will help us "budget" our time and "jobs."
-We always know how many "Jobs" are going to be in the Month
-The amount of "Jobs" are Different Monthly
-We only perform "Jobs" m-f (5days)
Danny