    Productivity Formula Help

    Hello Experts,

    I have changed my productivity spreadsheet to include start and finish times and now I can't work out the productivity correctly. Before we were manually typing in 2.5 if it took 2 and a half hours and now the time formula it says 2 hours 30 minutes.

    For example:

    6000 units scanned / 5 team / 2.5 hours to complete = 480 units per team member per hour

    Now in the new template that automatically works out the hours and minutes based on the start and finish times

    6000 units scanned / 5 team / Took 2 hours 30 minutes to complete = 11520 units per team member per hour which is very wrong.

    I just need help with if I need to change the formula or change the formatting of the cells as we keep track of stocktake productivity for 150 stores.

    Thanks so much!
    Attached Files Attached Files

  2. #2
    Forum Moderator
    Join Date
    01-21-2014
    Location
    St. Joseph, Illinois U.S.A.
    MS-Off Ver
    Office 365 v 2403
    Posts
    13,406

    Re: Productivity Formula Help

    You will need to convert the time into the integer hours you had in the first worksheet.

    Try in E8 =(D8-C8)*24

    If you are not aware of it times in Excel are numbers --- the decimal fraction of a day (24 hours).

    Expressed as integer hours as in your first workbook:
    17.5/24=0.729166666666667 =formatted for time 5:30 PM
    20/24=0.833333333333333 =formatted for time 8:00 PM

    (20-17.5)=2.5
    2.5/24 = 0.104166666666667 =formatted hours:minutes (h:mm) 2:30

    The formatting is cosmetic. It has no affect upon the underlying values.

    To get the results of actual time returned as whole numbers multiply the times by 24.
    Dave

+ Reply to Thread

Thread Information

Users Browsing this Thread

There are currently 1 users browsing this thread. (0 members and 1 guests)

Similar Threads

  1. Need formula for productivity calculation
    By Arunkumaramk in forum Excel Formulas & Functions
    Replies: 14
    Last Post: 03-24-2019, 10:08 AM
  2. [SOLVED] Formula for Employees' Productivity
    By Restie in forum Excel General
    Replies: 13
    Last Post: 10-27-2018, 11:03 PM
  3. Productivity formula
    By traxan in forum Excel Formulas & Functions
    Replies: 6
    Last Post: 01-02-2014, 11:15 AM
  4. Need formula to figure productivity
    By capecodtrixi in forum Excel Formulas & Functions
    Replies: 1
    Last Post: 04-14-2013, 07:20 PM
  5. Productivity Formula
    By Warehouse Dan in forum Excel General
    Replies: 5
    Last Post: 04-03-2012, 10:01 PM
  6. Productivity Percentage Formula
    By TruStylz in forum Excel General
    Replies: 11
    Last Post: 04-28-2011, 09:27 AM
  7. productivity formula
    By sccottt in forum Excel General
    Replies: 7
    Last Post: 10-01-2010, 06:58 AM

Tags for this Thread

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts

Search Engine Friendly URLs by vBSEO 3.6.0 RC 1